“ASIС” operated at these building sites
EXPOFORUM Convention and Exhibition Centre — from April 2012 to October 2014
CONTROL AREA – 250,000 sq.m. PROJECT LOCATION – Saint Petersburg, Peterburgskoye Highway, 64/1. SCOPE OF CONTROL – deviations in schedule, quality, and safety. Budget optimization oversight. RESULT – The project was successfully commissioned.
APARTMENT COMPLEX YE'S – from May 2013 to May 2014
CONTROL AREA – 84,000 sq. m. OBJECT LOCATION – Saint Petersburg, Khoshimina St., 14. SUBJECT OF CONTROL – Schedule deviations, quality and safety, oversight of optimization, oversight of budget execution. RESULT – The project was successfully commissioned.
Residential Complex "Vesna" – from June 2013 to March 2015
CONTROL AREA – 211,000 sq.m. PROJECT LOCATION – Leningrad Region, Kudrovo settlement SCOPE OF CONTROL – Deviations in schedule, quality, and safety; oversight of optimization; monitoring of budget execution. Deviations in schedule, quality, and safety; optimization control. Contract management – coordination of planning meetings. RESULT – The project was successfully commissioned.
Residential Complex "Novoye Murino" — from January 2014 to March 2017
CONTROL AREA – 309,000 sq.m. PROJECT LOCATION – Leningrad Region, Murino settlement SCOPE OF CONTROL – Deviations in schedule, quality, safety; optimization control; budget execution control. Deviations in schedule, quality, safety; optimization control. Contract management – management of planning meetings. RESULT – The project was successfully commissioned.
Residential Complex "Kantemirovsky" — from January 2014 to March 2016
CONTROL AREA – 277,000 sq.m. PROJECT LOCATION Saint Petersburg, M. Blyukhera Ave / Kushelevskaya Road SCOPE OF CONTROL – Schedule, quality, and safety deviations; optimization oversight; control over budget execution. Schedule, quality, and safety deviations; optimization oversight. Contract management – Management of planning meetings RESULT – The project was successfully commissioned
Residential Complex "Swallow’s Nest" - from August 2014 to July 2015
CONTROL AREA – 90,000 sq.m. PROJECT LOCATION: Saint Petersburg, Oktyabrskaya Embankment, 118 SCOPE OF CONTROL – Deviations in schedule, quality, and safety; control of optimization; control of budget execution. Deviations in schedule, quality, and safety; optimization control. Contract management – Management of coordination meetings. RESULT – The project was successfully commissioned.
Residential Complex "Tsarskaya Stolitsa" – from April 2015 to November 2015.
CONTROL AREA – 55,000 sq.m. OBJECT LOCATION: Saint Petersburg, Poltavsky Passage, bldg. 2 / Kremenchugskaya St. SCOPE OF CONTROL – Execution of finishing works with quality control of contractors. RESULT – The project was successfully commissioned.
Residential complex “Novy Okkervil” — from July 2015 through August 2015
CONTROL AREA – 55,000 sq.m. OBJECT LOCATION Leningrad Oblast, Kudrovo settlement CONTROL SCOPE – Deviations in schedule, quality, and safety; optimization oversight. RESULT – The project was successfully commissioned.
Park “Patriot” — from March 2015 to April 2015
CONTROL AREA – 30,000 sq.m. SITE LOCATION: Moscow Region, Kubinka settlement SUBJECT OF CONTROL – The project was unable to operate within a Unified Information Environment RESULT – The project was successfully commissioned and put into operation
Residential complex “Murinsky Posad, Building A” — from March 2015 to April 2015
CONTROL AREA – 51,000 sq.m. OBJECT LOCATION: Leningrad Region, Lavriki Highway CONTROL SCOPE – Schedule, quality, and safety deviations; optimization oversight. Contract management – Management of planning meetings RESULT – The project was successfully commissioned
Residential Complex "Vesna 2" – from March 2015 to September 2017
CONTROLLED AREA – 80,000 sq.m. FACILITY LOCATION Leningrad Oblast, Yanino settlement SCOPE OF CONTROL – Schedule, quality, and safety deviations; optimization oversight. CONTRACT MANAGEMENT – Management of coordination meetings. RESULT – The project was successfully commissioned.
Residential complex “Murinsky Posad, Buildings 1, 2, 3” — from July 2015 to Dec. 2018
CONTROLLED AREA – 270,000 sq.m. PROJECT LOCATION: Leningrad Region, Lavriki Highway SCOPE OF CONTROL – Schedule, quality, and safety deviations; optimization oversight. Contract management – Coordination of planning meetings RESULT – The project was successfully commissioned
Residential complex “New Horizons” — from March 2016 to September 2017
CONTROL AREA – 51,000 sq.m. OBJECT LOCATION: Leningrad Oblast, Lavriki Highway SUBJECT OF CONTROL – Schedule, quality, and safety deviations; optimization oversight. Contract management – Planning meeting management RESULT – The project was successfully commissioned
Residential complex "Nuevo Yanino", blocks G and D, from March 2016 to December 2017
CONTROL AREA – 170,000 sq.m. OBJECT LOCATION – Leningrad Region, Yanino settlement SCOPE OF CONTROL – Deviations in schedule, quality, and safety; supervision of concealed works RESULT – The project was successfully commissioned
Residential complex “Prinevsky” 5 buildings – from March 2016 to November 2018
CONTROL AREA – 53,000 sq.m. PROJECT LOCATION – Saint Petersburg, Oktyabrskaya Embankment / Rusanovskaya Street SCOPE OF CONTROL – Deviations in schedule, quality, safety; supervision of concealed works RESULT – The project was successfully commissioned and put into operation
Residential complex “Novaya Okhta” — from June 2016 to September 2016
CONTROL AREA – 113,000 sq.m. OBJECT LOCATION: Leningrad Region, Murino settlement SCOPE OF CONTROL – Schedule deviations, quality and safety, supervision of concealed works RESULT – The project was successfully commissioned
Residential complex “London” — from August 2016 to June 2017
CONTROL AREA – 118,000 sq.m. PROJECT LOCATION: Leningrad Region, Kudrovo settlement SCOPE OF CONTROL – Deviations in schedule, quality, and safety; optimization oversight. Contract Management – Management of planning meetings. RESULT – The project was successfully commissioned.
Residential Complex “Vesna 3” — from August 2016 to November 2018
CONTROL AREA – 47,000 sq.m. PROJECT LOCATION – Leningrad Region, Kudrovo settlement SCOPE OF CONTROL – Deviations in schedule, quality, and safety; supervision of concealed works RESULT – The project was successfully commissioned
Residential Complex "Riverside" — from August 2016 to November 2018
CONTROL AREA – 18,000 sq.m. FACILITY LOCATION – Saint Petersburg, Ushakovskaya Embankment, bldg. 5 SUBJECT OF CONTROL – Schedule, quality, and safety deviations; optimization oversight. Contract management – Management of planning meetings RESULT – A unified information environment has been implemented
Residential Complex "Chistoe Nebo", Phase 3 — from November 2016 to January 2018
CONTROL AREA – 170,000 sq.m. FACILITY LOCATION – Saint Petersburg, Komendantsky Ave / Plesetskaya St. SCOPE OF CONTROL – Deviations in schedule, quality, and safety; supervision of concealed works. RESULT – The facility was successfully commissioned.
Residential Complex “Arkazhskaya Sloboda” — from November 2016 to January 2018
CONTROL AREA – 22,000 sq.m. OBJECT LOCATION – Veliky Novgorod, Yuryevskoye Highway SUBJECT OF CONTROL – Analysis of the required resources and finances to complete the project RESULT – Implementation of a unified information space
Residential Complex “Chistoe Nebo”, Phase 5 — from August 2017 to March 2018
CONTROL AREA – 190,000 sq.m. OBJECT LOCATION – Saint Petersburg, Komendantsky Ave / Plesetskaya St. SCOPE OF CONTROL – Deviations in schedule, quality, and safety; optimization control. Contract Management – Management of planning meetings. RESULT – The facility was successfully commissioned.
Residential complex "Prinevsky" 6 buildings – from August 2017 to February 2019
CONTROL AREA – 93,000 sq.m. PROJECT LOCATION – Saint Petersburg, Oktyabrskaya Embankment / Rusanovskaya St. SCOPE OF CONTROL – Schedule, quality, and safety deviations; optimization oversight. CONTRACT MANAGEMENT – Management of coordination meetings. RESULT – The facility was successfully commissioned.
Residential complex “Novoye Yanino”, buildings A, B, V — from November 2017 to February 2019
CONTROL AREA – 195,000 sq.m. OBJECT LOCATION – Leningrad Region, Yanino settlement SUBJECT OF CONTROL – The facility has been successfully commissioned RESULT – The facility has been successfully commissioned
Residential Complex “Sunny City”, Phase 4 — from April 2018 to December 2018
CONTROL AREA – 95,500 sq.m. SITE LOCATION – Saint Petersburg, Krasnoselsky District, Peterhofskoye Highway SCOPE OF CONTROL – Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – Client Lab Team; ASIC organizational model – Technical Supervision, Client, and General Contractor Service
Residential complex "Polyustrovo Park" – Phase 3 – from April 2018 to December 2018
CONTROL AREA – 36,800 sq.m. SITE LOCATION – Saint Petersburg, Kalininsky District, Kondratievsky Ave., 68 SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – Client Lab Team, ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential complex “Palazzo”, Phase 1 — from April 2018 to December 2018
CONTROL AREA – 127,900 sq. m. PROJECT LOCATION – Saint Petersburg, Vasilievsky District, 25th Line of V.O., Bldg. 8 SCOPE OF CONTROL – Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – Client Lab Team, ASIC organizational model – Technical Supervision, Client, and General Contractor Service
Residential complex “Palacio”, phase 2 – from May 2018 to December 2018
CONTROL AREA – 95,000 sq.m. PROJECT LOCATION – Saint Petersburg, Vasileostrovsky District, 25th Line of V.O., bldg. 8 SUBJECT OF CONTROL – Implementation of a full Digitalization platform for the Client, General Contractor, and Technical Supervision RESULT – Organizational model ASIC – Technical Supervision, Client, and General Contractor Service
Residential Complex "Sunny City", Phase 8 - from May 2018 to December 2018
CONTROL AREA – 165,900 sq.m. OBJECT LOCATION - Saint Petersburg, Krasnoselsky District, Peterhof Highway SCOPE OF CONTROL - Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT - Organizational model of ASIC - Technical Supervision, Client, and General Contractor Service
Residential Complex “Chistoye Nebo”, Phase 4 — from May 2018 to December 2018
CONTROL AREA – 151,500 sq.m. PROJECT LOCATION – Saint Petersburg, Primorsky District, Kamenka, Komendantsky Ave., plots 1 and 2 SCOPE OF CONTROL – Implementation of a full Digitalization platform for the Client, General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex “Greenlandia-2”, Phase 9 — from May 2018 to December 2018
CONTROL AREA – 115,500 sq.m. OBJECT LOCATION – Leningrad Region, Vsevolozhsky District, Murino, Murino, plot 51, plot 53, plot 54, plot 55 SUBJECT OF CONTROL – Implementation of a full Digitalization platform for the Client, General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex “More Okean” — from May 2018 to December 2018
CONTROL AREA – 97,000 sq.m. PROJECT LOCATION – Saint Petersburg, Primorsky District, Yakhennaya Street. SUBJECT OF CONTROL – Implementation of a full digitalization platform for the Client, General Contractor, and Technical Supervision. RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor.
Residential Complex “Nevskie Parusa” — from May 2018 to December 2018
CONTROL AREA – 118,000 sq m. OBJECT LOCATION – Saint Petersburg, Nevsky District, Sovetsky Ave., bldg. 32 CONTROL SCOPE – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex "Moscow" – from May 2018 to December 2018
CONTROL AREA – 82,500 sq.m. PROJECT LOCATION – Saint Petersburg, Moskovsky District, Kostyushko St. / Varshavskaya St. SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Construction Supervision RESULT – ASIC organizational model – Construction Supervision, Client, and General Contractor Service
Residential complex “Philosophy” – from May 2018 to December 2018
CONTROL AREA – 107,000 sq.m. OBJECT LOCATION - Saint Petersburg, Moskovsky District, 1st Predportovy Drive, building 11, lit. A SUBJECT OF CONTROL - Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT - ASIC Organizational Model - Technical Supervision, Client, and General Contractor Service
Residential Complex “Sunny City” – Phase 9 – from May 2018 to December 2018
CONTROL AREA – 103,500 sq.m. OBJECT LOCATION – Saint Petersburg, Krasnoselsky District, Peterhofskoye Highway SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex “Chistoye Nebo”, Phase 7 — from May 2018 to December 2018
CONTROL AREA – 110,000 sq.m. OBJECT LOCATION – Saint Petersburg, Primorsky District, Kamenka, Komendantsky Ave., plots 1 and 2 SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential complex "Oblaka na Lesnoy" - from May 2018 to December 2018
CONTROL AREA – 85,000 sq.m. FACILITY LOCATION – Saint Petersburg, Vyborgsky District, Novolitovskaya St., Building 16 SCOPE OF CONTROL – Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential complex "Pritiazhenie" – from May 2018 to December 2018
CONTROL AREA – 180,000 sq.m. FACILITY LOCATION – Saint Petersburg, Vyborgsky District, Bolshoy Sampsonievsky Prospekt SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex “Fortetsiya” — from May 2018 to December 2018
CONTROL AREA – 44,500 sq.m. FACILITY LOCATION – Saint Petersburg, Kronstadt District, Kronstadt, Toulonskaya Alley, Building 2, Lit. V SUBJECT OF CONTROL – Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – Organizational model ASIC – Technical Supervision Service, Client, and General Contractor
Residential Complex “Solnechny Gorod” – Phase 5 – from May 2018 to December 2018
CONTROL AREA – 95,400 sq.m. FACILITY LOCATION – Saint Petersburg, Krasnoselsky District, Peterhof Highway SUBJECT OF CONTROL – Implementation of a full digitalization platform for the Client, General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision, Client, and General Contractor services
Residential Complex “Sunny City” – Phase 6 – from May 2018 to December 2018
CONTROL AREA – 135,500 sq.m. PROJECT LOCATION – Saint Petersburg, Krasnoselsky District, Peterhof Highway SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision Service, Client, and General Contractor
Residential Complex "Sunny City" – Phase 7 - from May 2018 to December 2018
CONTROL AREA – 166,000 sq.m. PROJECT LOCATION – Saint Petersburg, Krasnoselsky District, Peterhof Highway SCOPE OF CONTROL – Implementation of a full digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision, Client, and General Contractor Service
Residential complex “Zima Leto” – Building 4 – from May 2018 to December 2018
CONTROL AREA – 43,500 sq.m. OBJECT LOCATION – Saint Petersburg, Krasnogvardeysky District, Energetikov St., 9 CONTROL SCOPE – Implementation of a full Digitalization platform for the Client, the General Contractor, and Technical Supervision RESULT – ASIC organizational model – Technical Supervision, Client, and General Contractor Service
"Primary and secondary education facility with 825 seats" - from February 2019 to the present
CONTROL AREA - 279.03 sq.m. LOCATION OF THE OBJECT - St. Petersburg, Kosmonavtov Avenue, plot 228 (north of 61, building 1, letter A on Kosmonavtov Avenue), plot 1 (opposite 58, letter A on Kosmonavtov Avenue) in the 10th district, east of Yuri Gagarin Avenue. SUBJECT OF CONTROL - Remote control of the state order. RESULT - Implementation of Digital Technical Supervision
Greenlandia-2 LCD Phase 8 - from May 2018 to December 2018
CONTROL AREA - 88,500 sq.m. LOCATION OF THE OBJECT - Leningrad Region, Vsevolozhsky District, Murino, Murino, uch.51, uch.53, uch.54, uch.55 SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision RESULT - ASIC organizational model - Technical Supervision, Customer, and General Contractor Service
Greenlandia-2 LCD Phase 10 - from May 2018 to December 2018
CONTROL AREA - 113,000 sq.m. LOCATION OF THE OBJECT - Leningrad Region, Vsevolozhsky District, Murino, Murino, uch.51, uch.53, uch.54, uch.55 SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision RESULT - ASIC organizational model - Technical Supervision, Customer, and General Contractor Service
Petrovsky Quarter on the Water - from May 2018 to December 2018
CONTROL AREA - 163,000 sq.m. LOCATION OF THE OBJECT - St. Petersburg, Petrogradsky District, Petrovsky Prospekt 26 SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision RESULT - Organizational model of ASIC - Technical Supervision, Customer, and General Contractor Service
Moscow Residential Complex - from May 2018 to December 2018
CONTROL AREA - 34180 sq.m. LOCATION OF THE OBJECT - St. Petersburg, Pulkovo Highway, 30, Building B, Site 3 SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision RESULT - Organizational model of ASIC - Technical Supervision, Customer, and General Contractor Service
Artline LCD - from May 2018 to December 2018
CONTROL AREA - 328318.51 sq.m. LOCATION OF THE OBJECT - St. Petersburg, Torfyanaya Road, 17, lit. A. SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision. RESULT - Organizational model of ASIC - Technical Supervision Service, Customer, and General Contractor
Pulse on the Embankment Residential Complex - from May 2018 to December 2018
CONTROL AREA - 189517.83 sq.m. LOCATION OF THE OBJECT - Saint Petersburg, Oktyabrskaya Naberezhnaya SUBJECT OF CONTROL - Implementation of a complete digitalization platform for the Customer, General Contractor, and Technical Supervision RESULT - Organizational model of ASIC - Technical Supervision Service, Customer, and General Contractor
How is the information from the facility being provided now?
All existing tools represent "System Document Management," where a person/expert enters their decision or opinion. This approach is used by all BIM (3D) designers who try to implement "office-based solutions" on construction sites.

Our approach focuses on automating the control of the person who enters information into the system. This is possible through the use of statistical sampling algorithms and comparison algorithms for monitoring results.

Over the past few years, BIM has made significant progress in the design process.

BIM for architectural and construction control has also advanced to solutions such as BIM 365, etc.

These solutions, unlike ASIC products, rely solely on "human will," which significantly increases the requirements for personnel expertise and can lead to information distortion.

In ASIC products, the entire functionality is based on the generation of "hypotheses" and "scenarios."

Project management and control composition are conducted under the supervision of automated project management.

As a result, deviations are recorded digitally, without the influence of human factors.

Obtaining information without the influence of the human factor
Objective control exists only when information is transferred from a person to a machine and from a machine back to a person.

This is the only way to achieve objective statistical control, which can be transmitted over long distances without distortion.

The ASIC platform allows you to build information models for construction projects and maintain a shared information space among all project participants.

ASIC - REMOTE STATISTICAL CONTROL MACHINE

How does the unified information field for managing a construction project work?
Creating a digital object structure
Use this tool to create the necessary depth of further statistical control.
Equating types of work
Use this tool to display your project's work types in a standardized format.
Linking the "pies" of process maps to the structure of the object
BY USING THIS TOOL, WE CAN CREATE CONTROL POINTS THAT WILL TELL US THE TYPES, LABOR COSTS, AND VOLUMES OF ALL TYPES OF WORK AT THE LOCATIONS OF THE OBJECT.
Simulation of the work schedule
The schedule is created based on the types of work in the project, and we will create a control schedule for it.
Creating a control schedule
The control schedule is based on the "virtual points" of each room's location.
Execution of the control schedule
TRAINED BY A STANDARDIZED METHOD UNDER THE CONTROL OF THE SYSTEM'S ALGORITHMS, THE CONTROLLER RECORDS THE ACTUAL DATA ON THE PERFORMANCE OF WORK ON EACH STANDARD TECHNOLOGICAL MAP AT ALL CONTROL POINTS OF THE CONTROL SCHEDULE.
Automatic processing of the received information
The information from the controller gets to the server and the system's algorithms generate the appropriate help:

  • Deviations by TTK, locations, and performers - time and volume.
  • Deviations by TTK, locations, and performers - time and quality.
Sending the received information
THE HELP GETS INTO THE ANALYSIS MATRIX AND, BASED ON THE RESULT, RECEIVES ONE OR ANOTHER INDICATION ON THE OBJECT PLAN. THE RECEIVED REPORTS ARE SENT TO THE RESPONSIBLE EMPLOYEES ACCORDING TO THE ACCESS LEVEL.

  • Generation of a "Construction Site Security Monitoring Schedule";
  • Execution in parallel with the "ASIC Control Schedule" and "Site Safety Control Schedule";
  • Generation of the Report "ASIC Site Construction Safety".
Interpretation of statistical information
ASIC STARTUP 3.33 GENERATES A REPORT IN ITS INITIAL VERSION, ON THE BASIS OF WHICH REGULAR MEETINGS CAN BE HELD. THE REPORT WILL SHOW THE SOURCE OF EACH DEVIATION IN TIME AND QUALITY OF THE QMS.
STATISTICAL
MACHINE CONTROL
NOW, INSTEAD OF REPORTS FROM EMPLOYEES, YOU WILL RECEIVE INFORMATION GENERATED BY THE SYSTEM'S ALGORITHMS ABOUT THE REAL PICTURE OF ALL THE QMS AT THE CONTROL FACILITY.
The planning sessions will show a real Fact-Plan for the facility, detailing the reasons for the deviation to the specific types of work of each contractor on a specific floor, in any apartment, room.
To obtain an objective picture from the construction site, you will need:
PREPARE
an employee according
to the instructions
Configure
an ASIC machine according to the instructions
Start
the machine to carry out monitoring of compliance with the schedules
for data loading
Provide the results
in the form of a report
MACHINE STATISTICAL CONTROL IS FULLY AVAILABLE OUT OF THE BOX
THIS IS POSSIBLE BECAUSE “ASIC” WAS CREATED BY BUILDERS FOR BUILDERS.

The boxed version of "ASIC" includes hardware with preinstalled software and job descriptions for employees.

The boxed version includes:
  • Laptop
  • 2 smartphones
  • “ASIC” instruction manual
  • Documentation for the Chief Engineer
  • Documentation for the Project Manager
  • Documentation for the Chief Financial Officer
  • Documentation for the Director of Development
  • Documentation for the IT Director
  • Implementation of ASIС StartUp 3.33 is not required!
    You only need to familiarize yourself with the instructions and perform a test setup of the system for further work on your project.
    1 day
    1 day
    Conclusion of a contract
    3 day
    3 day
    Delivery of the “ASIC” case
    4 -6 days
    4 -6 days
    Reading instructions
    The instructions are designed so that specialists can freely use the information model “ASIC”, just as they use a stove in the kitchen.
    6 - 14 days
    6 - 14 days
    Test setup of a digital model
    During the test configuration stage, any misunderstandings encountered while working with the digital model will be identified, and our support engineers will help resolve them. They will be available both to answer your questions and to provide hands-on assistance with the setup.
    from 15 day
    from 15 day
    Using “ASIC” on your real data
    Facilities in the Northwest were commissioned using ASIC control
    Construction volumes were commissioned
    Savings were achieved on each facility from investment expenditures
    58
    6 303 608 sq.m.
    from 15 to 25%
    Our experience
    Achievements of machine statistical control
    over 9 years
    Made on
    Tilda